Nestlé Batik & Spark

Project: Nestlé Batik & Spark
Location:
Batang, Central Java
Client: PT Nestlé  Indonesia
Contract period: Jul 2021 – Aug 2022

Scope of work:
Construct Only – Earthworks, Concrete and Steel Structure (including PEB), Architectural, External and coordination of MEP and Process Works.

Contract sum: US$ 19 million
GFA: 36,000 m2

A contract to deliver the construction of new greenfield Plant in Batang, Central Java for PT Nestlé Indonesia.

Decorient was appointed to deliver a dairy processing plant which includes production building, warehouse, office, and ancillary buildings with total gross floor area of 36,000 sqm on a site of approximately 20 hectares. The plant will be one of the first industrial buildings to be built at the new industrial complex in Central Java, namely Batang Industrial Park.

The new plant is designed by Meinhardt, who will also act as the Engineer for the clients during construction. This will be the fourth Nestlé plant operating in the country.

Nestlé new plant project will take 12 months to complete and partial taking-over to allow for Client’s process equipment installation will happen early next year. As the main contractor, Decorient’s scope of works will be structure, architectural, external works and coordination of the MEP and process equipment packages. 

From 1992 to 2003, Decorient was involved in three phases of construction of Nestlé plant in Kejayan, Pasuruan, East Java.