Cargill Bromo and Quantum Leap

Project: Cargill Bromo & Quantum Leap
Location:
Gresik, East Java
Client: PT Cargill Indonesia
Contract period:January 2022 – April 2023

Scope of work:
Construct Only – Civil, Structural, Architectural

Contract sum: US$ 5 million
GFA: 3,400 m2

PT Cargill Indonesia, a subsidiary of Cargill Corporation has appointed PT Decorient Partaya Indonesia as the main contractor to deliver the expansion of Cargill Cocoa & Chocolate existing plant in Gresik, East Java, Indonesia.

Decorient will deliver an expansion of cocoa & chocolate processing plant which consists of two packages, codenamed Bromo and Quantum Leap. The Bromo Package consists of extension of production building, construction of a chemical mixing building, tank foundation, powerhouse, a canteen on a site of the existing plant and external works like cut and fill, road and drainage work. The Quantum Leap Package consists of the construction of a new laboratory building adjacent to the existing production building.

Construction will take approximately 15 months to complete and partial taking-over to allow for Client’s process equipment installation will happen during the period of construction. As the main contractor, Decorient’s scope of works will be foundation, structure, architectural, external works and coordination of the MEP and process equipment packages. 

Royal HaskoningDHV is the designer of the facilities and will act as the Engineer for the clients during construction.